DESCRIPTION:
THE EXTERNAL DRAINAGE CONNECTIONS TO THE EXISTING THAMES WATER SEWERS.
This comprised the construction of 3 new manholes and sewers to connect the site drainage to the existing sewers. These works included the excavation of shafts and headings and the construction of deep drainage.
This comprised the construction of 3 new manholes and sewers to connect the site drainage to the existing sewers. These works included the excavation of shafts and headings and the construction of deep drainage.
EXTERNAL HARD LANDSCAPING AND SURFACE WATER DRAINAGE.
This comprised of large areas of varied concrete paving to pedestrian areas including external stairs with tactile paving, safety nosings, additionally porous resin bound aggregate paving. Macadam surfacing to pedestrian areas and porous macadam to an elevated sports area.
This comprised of large areas of varied concrete paving to pedestrian areas including external stairs with tactile paving, safety nosings, additionally porous resin bound aggregate paving. Macadam surfacing to pedestrian areas and porous macadam to an elevated sports area.
New drainage and the installation of extensive ACCO drainage and soakaways for surface water and connections to the new drainage or rainwater harvesting system. Installation of tree pit pcc linings and bank retention works involving geotextile stabilisation, gabions and RC pile capping beam.
CLIENT:
Girls’ Day School Trust
South Hampstead High School
3 Maresfield Garden
Hampstead
London NW3 5SS
Girls’ Day School Trust
South Hampstead High School
3 Maresfield Garden
Hampstead
London NW3 5SS
CONTRACTOR:
Wates Construction Limited
Wates Construction Limited
WORKS:
Enabling works, demolition of existing buildings and the construction of a new art and design block, building entrance, teaching block, basement level sports hall and associated external works.
Enabling works, demolition of existing buildings and the construction of a new art and design block, building entrance, teaching block, basement level sports hall and associated external works.
“I would like to thank you and your team on the completion of your works with the final application of the surface finish to the MUGA pitch over the Easter Holiday, the netball court looks fantastic. I commend you and your team on the high quality of work achieved at South Hampstead High School in what was a very condensed programme on a logistically challenging site. Please extend my thanks to Richard for his positive attitude with suggestions and solutions to problems encountered. I look forward to working with you again in the future.”
Wayne Farnfield, Project Manager
Wates Construction London & Kent