Elephant & Castle, London

DESCRIPTION:
Underpinning and drainage connection.
The project involved three number shafts and 7 number headings for the connection between the manholes and branches.
Two number shafts where 1.4m depth, with the main shaft connecting to the main FW run, at 2.4m depth, as well as headings varying from 1m to 9m.
All of the headings were constructed under an existing 400mm RC slab (saving our client time and budget).
We overcame all obstructions and delivered the job to a high standard, to our clients satisfaction.
LOCATION:
Dryden Court
Elephant & Castle, London

Don't miss...